ID Description Savings Cost Payback Status
(1-9)
AS0391 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS $14,162 $625 0.0 N
AS0391 DEVELOP STANDARD OPERATING PROCEDURES $121,316 $80,000 0.7 N
MA0556 IMPROVE SPACE COMFORT CONDITIONING $17,360 $17,910 1.0 N
SD0248 INSTALL EQUIPMENT TO MOVE PRODUCT $70,500 $120,000 1.7 N
SD0248 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $743 $800 1.1 N
SD0248 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $11,600 $1,000 0.1 I
SD0248 INSTALL SYSTEM TO COLLECT SCRAP $13,426 $11,836 0.9 I
UF0226 PAY BILLS ON TIME TO AVOID LATE FEES $1,863 $0 0.0 N
UF0226 INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM $78,207 $22,390 0.3 N