SEARCH: Recommendations


121 Recommendations Found

RESET

Year
ARC Code
SIC Code
NAICS Code
Savings
Imp Cost
Select State
Imp Status
Filter by Center
Per Page
ID Description Savings Cost Payback Status
(1-25) Next 25 >
TT0108 CONSIDER POWER LOSS AS WELL AS INITIAL LOADS AND LOAD GROWTH IN DOWN-SIZING TRANSFORMERS $5,367 $8,075 1.5
UA0094 OPTIMIZE PLANT POWER FACTOR $6,000 $14,980 2.5
UMS012 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST $553,000 $750,000 1.4
DL0054 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $15,225 $50 0.0 N
NC0403 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT $1,310,487 $0 0.0 N
WV0393 USE DEMAND CONTROLLER OR LOAD SHEDDER $4,441 $7,800 1.8 N
TT0030 USE POWER FACTOR CONTROLLERS $4,100 $22,600 5.5 N
TT0028 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT $993,250 $4,000,000 4.0 N
TT0028 USE POWER FACTOR CONTROLLERS $5,033 $23,900 4.7 N
LE0266 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,436 $2,500 1.7 N
NC0368 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT $42,586 $100,000 2.3 N
NC0367 USE STEAM PRESSURE REDUCTION TO GENERATE POWER $9,176 $30,000 3.3 N
NC0367 BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT $43,971 $100,000 2.3 N
MS0320 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT $49,454 $130,000 2.6 N
OK0747 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $7,099 $0 0.0 N
AM0528 OPTIMIZE PLANT POWER FACTOR $9,100 $5,920 0.7 I
MA0615 OPTIMIZE PLANT POWER FACTOR $4,673 $18,500 4.0 I
LE0248 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,500 $2,500 0.7 I
MS0305 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR $48,733 $70,000 1.4 N
NC0324 MAKE ICE DURING OFF PEAK HOURS FOR COOLING $1,571 $5,425 3.5 N
BD0287 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $146 $0 0.0 I
BD0285 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $488 $0 0.0 I
LE0202 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,378 $2,500 1.8 I
OK0696 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,344 $2,100 0.3 N
OK0683 USE POWER FACTOR CONTROLLERS $8,063 $7,713 1.0 I
(1-25) Next 25 >