ID Description Savings Cost Payback Impstatus
(1-25)Next 25 >
GT0870RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS$625$00.0n/a
GT0870REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED$4,570$1,0000.2n/a
GT0870UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS$9,245$20,0502.2n/a
GT0870INSTALL OCCUPANCY SENSORS$5,810$6200.1n/a
GT0870USE SYNTHETIC LUBRICANT$43,210$00.0n/a
GT0870CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES$1,500$6,3994.3n/a
GT0870UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS$33,910$45,0001.3n/a
GT0870RECOVER WASTE HEAT FROM EQUIPMENT$4,796$7,6561.6n/a
OK0784INSULATE BARE EQUIPMENT$32,802$10,6270.3n/a
OK0784REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES$26,522$23,8590.9n/a
OK0784USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS$11,003$00.0n/a
OK0784INSTALL OCCUPANCY SENSORS$1,600$6200.4n/a
OK0784INSTALL OCCUPANCY SENSORS$362$1,0132.8n/a
OK0784INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS$888$1,0981.2n/a
OK0784REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED$4,104$00.0n/a
OK0784ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES$2,038$00.0n/a
OK0784INSTALL TIMERS AND/OR THERMOSTATS$858$9901.2n/a
MA0653INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE)$110,550$270,0002.4n/a
MA0653INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE)$37,210$68,0001.8n/a
MA0653REDUCE VENTILATION AIR$16,188$7520.0n/a
MA0653CLOSE OFF UNNEEDED STEAM LINES$3,551$5000.1n/a
MA0653INSULATE BARE EQUIPMENT$2,840$7,5102.6n/a
MA0653USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS$2,375$6,1252.6n/a
GT0867UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS$52,318$89,9711.7n/a
GT0867INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS$8,794$4,0000.5n/a