Industrial Assessment Centers
Assessment #WV0414
| Assessment Year | 2010 |
|---|---|
| SIC | 3559 |
| SIC Description | Special Industry Machinery, Nec |
| NAICS | 333999 |
| NAICS Description | All Other Miscellaneous General Purpose Machinery Manufacturing |
| Principal Product | PVC fill media for cooling tower and waste water treatment |
| Sales | $ 25,000,000 |
| # of Employees | 92 |
| Plant Area (Sq.Ft.) | 120,000 |
| Annual Production | 22,000,000 Pounds |
| Production Hrs. Annual | 4,160 |
| Location (State) | WV |
| Yearly Energy Cost | $ 394,637 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
4,570,983 kWh | $ 180,561 | $ 0.040 /kWh |
- Demand Charge |
15,498 kW | $ 165,446 | $ 10.68 /kW |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
4,461 MMBtu | $ 48,630 | $ 10.90 /MMBtu |
TOTAL ENERGY |
51,314 MMBtu | $ 394,637 | $ 7.69 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
480,245 kWh 343,293 kWh |
$ 18,970 $ 13,561 |
10.51 % 7.51 % |
$ 0.040 /kWh |
- Demand Charge |
1,440 kW 1,007 kW |
$ 15,379 $ 10,755 |
9.30 % 6.50 % |
$ 10.68 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
2,984 MMBtu 160 MMBtu |
$ 32,137 $ 1,723 |
66.08 % 3.54 % |
$ 10.90 /MMBtu |
TOTAL ENERGY |
7,905 MMBtu 3,678 MMBtu |
$ 66,486 $ 26,039 |
16.85 % 6.60 % |
$ 7.69 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
RECOVER HEAT FROM OVEN EXHAUST / KILNS | 2.2432 | N | $ 18,300 | $ 22,889 | 0.80 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 02 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 42,420 | $ 12,304 | 3.45 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 03 | view details |
REDUCE FLUID FLOW RATES | 2.5123 | I | $ 280 | $ 7,185 | 0.04 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 04 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | N | $ 15,400 | $ 6,064 | 2.54 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 05 | view details |
RECOVER HEAT FROM COMPRESSED AIR DRYERS | 2.2435 | N | $ 400 | $ 3,414 | 0.12 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 06 | view details |
USE RADIANT HEATER FOR SPOT HEATING | 2.7231 | N | $ 5,310 | $ 3,403 | 1.56 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 07 | view details |
UTILIZE A LESS EXPENSIVE COOLING METHOD | 2.2628 | N | $ 14,000 | $ 2,505 | 5.59 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 08 | view details |
USE MORE EFFICIENT LIGHT SOURCE | 2.7143 | I | $ 3,614 | $ 1,467 | 2.46 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 09 | view details |
INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | 2.4221 | N | $ 835 | $ 1,409 | 0.59 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 10 | view details |
RECOVER MECHANICAL ENERGY | 2.4311 | I | $ 1,000 | $ 1,362 | 0.73 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 11 | view details |
REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | 2.7224 | I | $ 1,070 | $ 1,335 | 0.80 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 12 | view details |
DEVELOP A REPAIR/REPLACE POLICY | 2.4151 | I | $ 740 | $ 1,318 | 0.56 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 13 | view details |
IMPROVE LUBRICATION PRACTICES | 2.4312 | N | $ 465 | $ 413 | 1.13 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 14 | view details |
USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | 2.7492 | I | $ 1,735 | $ 388 | 4.47 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||