Industrial Assessment Centers
Assessment #WV0291
| Assessment Year | 2004 |
|---|---|
| SIC | 3317 |
| SIC Description | Steel Pipe And Tubes |
| NAICS | 331210 |
| NAICS Description | Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
| Principal Product | Welded Steal tubing |
| Sales | $ 18,500,000 |
| # of Employees | 82 |
| Plant Area (Sq.Ft.) | 210,000 |
| Annual Production | 32,000,000 Pounds |
| Production Hrs. Annual | 4,368 |
| Location (State) | OH |
| Yearly Energy Cost | $ 291,121 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
786,486 kWh | $ 215,692 | $ 0.274 /kWh |
- Demand Charge |
1,563 kW | $ 1,323 | $ 0.85 /kW |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
9,249 MMBtu | $ 74,106 | $ 8.01 /MMBtu |
TOTAL ENERGY |
17,310 MMBtu | $ 291,121 | $ 16.82 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
786,486 kWh 552,930 kWh |
$ 43,152 $ 28,836 |
20.01 % 13.37 % |
$ 0.274 /kWh |
- Demand Charge |
1,563 kW 838 kW |
$ 1,323 $ 975 |
100.00 % 73.70 % |
$ 0.85 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
0 MMBtu 0 MMBtu |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 8.01 /MMBtu |
TOTAL ENERGY |
8,061 MMBtu 5,667 MMBtu |
$ 44,475 $ 29,811 |
15.28 % 10.24 % |
$ 16.82 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | 2.4322 | I | $ 360 | $ 14,733 | 0.02 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 02 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | N | $ 1,032 | $ 9,255 | 0.11 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 03 | view details |
DEVELOP A REPAIR/REPLACE POLICY | 2.4151 | I | $ 0 | $ 6,488 | 0.00 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 04 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 4,824 | $ 5,578 | 0.86 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 05 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 0 | $ 2,186 | 0.00 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 06 | view details |
INSTALL OCCUPANCY SENSORS | 2.7135 | N | $ 1,316 | $ 1,720 | 0.77 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 07 | view details |
USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | 2.2614 | N | $ 5,205 | $ 1,519 | 3.43 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 08 | view details |
USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | 2.4133 | N | $ 116 | $ 1,485 | 0.08 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 09 | view details |
INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | 2.4221 | N | $ 747 | $ 685 | 1.09 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 10 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 100 | $ 550 | 0.18 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||