| Assessment Year | 1999 |
|---|---|
| SIC | 3366 |
| SIC Description | Copper Foundries |
| NAICS | |
| NAICS Description | |
| Principal Product | Aluminum, Bronze, and Copper Alloys |
| Sales | $ 40,000,000 |
| # of Employees | 254 |
| Plant Area (Sq.Ft.) | 550,190 |
| Annual Production | 14,000,000 Pounds |
| Production Hrs. Annual | 6,000 |
| Location (State) | WI |
| Yearly Energy Cost | $ 1,246,757 |
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
13,952,228 kWh | $ 363,578 | $ 0.026 /kWh |
- Demand Charge |
43,108 kW | $ 392,651 | $ 9.11 /kW |
- Electricity Fees |
- | $ 73,590 | - |
Natural Gas |
114,854 MMBtu | $ 416,938 | $ 3.63 /MMBtu |
TOTAL ENERGY |
257,864 MMBtu | $ 1,246,757 | $ 4.83 /MMBtu |
Water Disposal |
115,611,000 Gal | $ 98,683 | $ 0 /Gal |
Other Liquid (haz) |
36,000 Gal | $ 18,900 | $ 0 /Gal |
Solid Waste (non-haz) |
1,440,000 lbs | $ -83,400 | $ 0 /lbs |
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
65,651 kWh 38,394 kWh |
$ 1,806 $ 1,055 |
0.50 % 0.29 % |
$ 0.026 /kWh |
- Demand Charge |
595 kW 546 kW |
$ 5,757 $ 5,286 |
1.47 % 1.35 % |
$ 9.11 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
5,593 MMBtu 0 MMBtu |
$ 20,305 $ 0 |
4.87 % 0.00 % |
$ 3.63 /MMBtu |
TOTAL ENERGY |
6,266 MMBtu 394 MMBtu |
$ 27,868 $ 6,341 |
2.24 % 0.51 % |
$ 4.83 /MMBtu |
Water Disposal |
10,404,990 Gal 10,404,990 Gal |
$ 7,137 $ 7,137 |
7.23 % 7.23 % |
$ 0 /Gal |
Other Liquid (haz) |
33,120 Gal 0 Gal |
$ 17,388 $ 0 |
92.00 % 0.00 % |
$ 0 /Gal |
Solid Waste (non-haz) |
0 lbs 0 lbs |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 0 /lbs |
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
PAY BILLS ON TIME TO AVOID LATE FEES | 4.8210 | N | $ 0 | $ 26,146 | 0.00 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 02 | view details |
REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | 2.1221 | N | $ 72,000 | $ 21,494 | 3.35 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 03 | view details |
USE EVAPORATION TO CONCENTRATE MATERIAL | 3.3131 | N | $ 16,000 | $ 13,199 | 1.21 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 04 | view details |
REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | 3.4114 | I | $ 22,000 | $ 6,159 | 3.57 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 05 | view details |
RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | 2.3131 | I | $ 0 | $ 4,879 | 0.00 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 06 | view details |
INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | 2.4221 | I | $ 640 | $ 2,440 | 0.26 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 07 | view details |
UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | 2.4111 | N | $ 624 | $ 785 | 0.79 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 08 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | N | $ 243 | $ 437 | 0.56 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||