Assessment #UF0340
| Assessment Year | 2004 |
|---|---|
| SIC | 2011 |
| SIC Description | Meat Packing Plants |
| NAICS | 311611 |
| NAICS Description | Animal (except Poultry) Slaughtering |
| Principal Product | Processed Meat |
| Sales | $ 200,000,000 |
| # of Employees | 700 |
| Plant Area (Sq.Ft.) | 250,000 |
| Annual Production | 144,000,000 Pounds |
| Production Hrs. Annual | 6,240 |
| Location (State) | FL |
| Yearly Energy Cost | $ 3,361,973 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
31,439,730 kWh | $ 1,588,672 | $ 0.051 /kWh |
- Demand Charge |
60,047 kW | $ 439,998 | $ 7.33 /kW |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
195,385 MMBtu | $ 1,333,303 | $ 6.82 /MMBtu |
TOTAL ENERGY |
517,642 MMBtu | $ 3,361,973 | $ 6.49 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
13,368,034 kWh 786,478 kWh |
$ 895,409 $ 46,114 |
56.36 % 2.90 % |
$ 0.051 /kWh |
- Demand Charge |
1,810 kW 61 kW |
$ 172,361 $ 5,812 |
39.17 % 1.32 % |
$ 7.33 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
-34,135 MMBtu 0 MMBtu |
$ -232,641 $ 0 |
-17.45 % 0.00 % |
$ 6.82 /MMBtu |
TOTAL ENERGY |
102,887 MMBtu 8,061 MMBtu |
$ 835,129 $ 51,926 |
24.84 % 1.54 % |
$ 6.49 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT COMBUSTION AIR | 2.2411 | N | $ 170,000 | $ 122,549 | 1.39 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 02 | view details |
USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | 2.3417 | N | $ 2,420,000 | $ 617,545 | 3.92 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 03 | view details |
REPLACE THE CHLORINATION STAGE WITH AN OXYGEN OR OZONE STAGE | 3.4141 | N | $ 98,000 | $ 29,744 | 3.29 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 04 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 48,289 | $ 38,590 | 1.25 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 05 | view details |
USE POWER FACTOR CONTROLLERS | 2.3211 | I | $ 40,000 | $ 10,480 | 3.82 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 06 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 400 | $ 7,682 | 0.05 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 07 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | N | $ 37,572 | $ 7,109 | 5.29 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 08 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | I | $ 7,900 | $ 5,678 | 1.39 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||