Assessment #UA0026
| Assessment Year | 2008 |
|---|---|
| SIC | 3088 |
| SIC Description | Plastics Plumbing Fixtures |
| NAICS | 326191 |
| NAICS Description | Plastics Plumbing Fixture Manufacturing |
| Principal Product | Bathtubs, Sinks |
| Sales | $ 1 |
| # of Employees | 350 |
| Plant Area (Sq.Ft.) | 517,000 |
| Annual Production | 1 Not Available |
| Production Hrs. Annual | 6,240 |
| Location (State) | AL |
| Yearly Energy Cost | $ 2,447,755 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
20,680,856 kWh | $ 874,459 | $ 0.042 /kWh |
- Demand Charge |
28,210 kW | $ 463,630 | $ 16.43 /kW |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
128,073 MMBtu | $ 1,109,666 | $ 8.66 /MMBtu |
TOTAL ENERGY |
340,052 MMBtu | $ 2,447,755 | $ 7.20 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
1,682,771 kWh 178,473 kWh |
$ 76,421 $ 7,546 |
8.74 % 0.86 % |
$ 0.042 /kWh |
- Demand Charge |
326 kW 326 kW |
$ 4,111 $ 4,111 |
0.89 % 0.89 % |
$ 16.43 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
28,618 MMBtu 3,214 MMBtu |
$ 247,790 $ 27,831 |
22.33 % 2.51 % |
$ 8.66 /MMBtu |
TOTAL ENERGY |
45,866 MMBtu 5,043 MMBtu |
$ 328,322 $ 39,488 |
13.41 % 1.61 % |
$ 7.20 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
REPAIR LEAKS IN LINES AND VALVES | 2.2133 | I | $ 950 | $ 27,831 | 0.03 | ||||||||||||||||
|
|||||||||||||||||||||||
| 02 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | N | $ 170,829 | $ 60,701 | 2.81 | ||||||||||||||||
|
|||||||||||||||||||||||
| 03 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | N | $ 58,587 | $ 8,174 | 7.17 | ||||||||||||||||
|
|||||||||||||||||||||||
| 04 | view details |
INSULATE BARE EQUIPMENT | 2.2511 | N | $ 32,592 | $ 170,363 | 0.19 | ||||||||||||||||
|
|||||||||||||||||||||||
| 05 | view details |
INSULATE STEAM / HOT WATER LINES | 2.2131 | N | $ 18,202 | $ 49,596 | 0.37 | ||||||||||||||||
|
|||||||||||||||||||||||
| 06 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 4,200 | $ 5,609 | 0.75 | ||||||||||||||||
|
|||||||||||||||||||||||
| 07 | view details |
REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | 2.4231 | I | $ 0 | $ 6,048 | 0.00 | ||||||||||||||||
|
|||||||||||||||||||||||