Industrial Assessment Centers
Assessment #TT0056
| Assessment Year | 2010 |
|---|---|
| SIC | 3541 |
| SIC Description | Machine Tools, Metal Cutting Types |
| NAICS | 333512 |
| NAICS Description | Machine Tool (Metal Cutting Types) Manufacturing |
| Principal Product | Tungsten Carbide Inserts |
| Sales | $ 1 |
| # of Employees | 1 |
| Plant Area (Sq.Ft.) | 40,000 |
| Annual Production | 1 Not Available |
| Production Hrs. Annual | 1 |
| Location (State) | TN |
| Yearly Energy Cost | $ 1,060,462 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
14,552,320 kWh | $ 1,048,899 | $ 0.072 /kWh |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
1,326 MMBtu | $ 11,563 | $ 8.72 /MMBtu |
TOTAL ENERGY |
150,489 MMBtu | $ 1,060,462 | $ 7.05 /MMBtu |
Water Disposal |
103,081 Gal | $ 85,241 | $ 1 /Gal |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
510,617 kWh 0 kWh |
$ 41,876 $ 0 |
3.99 % 0.00 % |
$ 0.072 /kWh |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
0 MMBtu 0 MMBtu |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 8.72 /MMBtu |
TOTAL ENERGY |
5,234 MMBtu 0 MMBtu |
$ 41,876 $ 0 |
3.95 % 0.00 % |
$ 7.05 /MMBtu |
Water Disposal |
0 Gal 0 Gal |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 1 /Gal |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | N | $ 11,208 | $ 2,872 | 3.90 | ||||||||||||
|
|||||||||||||||||||
| 02 | view details |
USE MORE EFFICIENT LIGHT SOURCE | 2.7143 | N | $ 45,225 | $ 10,661 | 4.24 | ||||||||||||
|
|||||||||||||||||||
| 03 | view details |
CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | 3.1191 | N | $ 1,444 | $ 8,445 | 0.17 | ||||||||||||
|
|||||||||||||||||||
| 04 | view details |
INSTALL SKYLIGHTS | 2.7145 | N | $ 88,000 | $ 16,932 | 5.20 | ||||||||||||
|
|||||||||||||||||||
| 05 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | N | $ 21,900 | $ 2,966 | 7.38 | ||||||||||||
|
|||||||||||||||||||