Industrial Assessment Centers
Assessment #TN0424
| Assessment Year | 1991 |
|---|---|
| SIC | 3545 |
| SIC Description | Machine Tool Accessories |
| NAICS | |
| NAICS Description | |
| Principal Product | DRILL CHUCKS |
| Sales | $ 50,000,000 |
| # of Employees | 445 |
| Plant Area (Sq.Ft.) | 0 |
| Annual Production | 8,000,000 Pieces |
| Production Hrs. Annual | 7,344 |
| Location (State) | SC |
| Yearly Energy Cost | $ 602,301 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
10,741,794 kWh | $ 518,517 | $ 0.048 /kWh |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
14,251 MMBtu | $ 72,602 | $ 5.09 /MMBtu |
Fuel Oil #2 |
1,567 MMBtu | $ 11,182 | $ 7.14 /MMBtu |
TOTAL ENERGY |
125,921 MMBtu | $ 602,301 | $ 4.78 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
1,577,373 kWh 1,577,373 kWh |
$ 56,134 $ 56,134 |
10.83 % 10.83 % |
$ 0.048 /kWh |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
0 MMBtu 0 MMBtu |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 5.09 /MMBtu |
Fuel Oil #2 |
2,029 MMBtu 2,029 MMBtu |
$ 14,489 $ 14,489 |
129.57 % 129.57 % |
$ 7.14 /MMBtu |
TOTAL ENERGY |
18,198 MMBtu 18,198 MMBtu |
$ 70,623 $ 70,623 |
11.73 % 11.73 % |
$ 4.78 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | 2.7226 | I | $ 8,500 | $ 29,757 | 0.29 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 02 | view details |
USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | 2.2425 | I | $ 17,000 | $ 11,182 | 1.52 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 03 | view details |
TURN OFF EQUIPMENT WHEN NOT IN USE | 2.6218 | I | $ 1,120 | $ 12,380 | 0.09 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 04 | view details |
INSULATE BARE EQUIPMENT | 2.2511 | I | $ 840 | $ 3,307 | 0.25 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 05 | view details |
IMPROVE LUBRICATION PRACTICES | 2.4312 | I | $ 4,500 | $ 3,278 | 1.37 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 06 | view details |
KEEP LAMPS AND REFLECTORS CLEAN | 2.7123 | I | $ 0 | $ 2,594 | 0.00 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 07 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 390 | $ 1,927 | 0.20 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 08 | view details |
INSTALL SET-BACK TIMERS | 2.6232 | I | $ 0 | $ 1,885 | 0.00 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 09 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 1,340 | $ 4,501 | 0.30 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||