Assessment #TA0116
| Assessment Year | 2006 |
|---|---|
| SIC | 3728 |
| SIC Description | Aircraft Parts And Equipment, Nec |
| NAICS | 336413 |
| NAICS Description | Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| Principal Product | Heavy truck Part and Assembly |
| Sales | $ 50,000,000 |
| # of Employees | 120 |
| Plant Area (Sq.Ft.) | 133,000 |
| Annual Production | 105,000 Pieces |
| Production Hrs. Annual | 4,980 |
| Location (State) | TX |
| Yearly Energy Cost | $ 607,825 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
5,431,414 kWh | $ 386,272 | $ 0.071 /kWh |
- Demand Charge |
14,411 kW | $ 82,635 | $ 5.73 /kW |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
9,240 MMBtu | $ 138,918 | $ 15.03 /MMBtu |
TOTAL ENERGY |
64,912 MMBtu | $ 607,825 | $ 9.36 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
331,949 kWh 0 kWh |
$ 21,962 $ 0 |
5.69 % 0.00 % |
$ 0.071 /kWh |
- Demand Charge |
1,258 kW 0 kW |
$ 7,203 $ 0 |
8.72 % 0.00 % |
$ 5.73 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
0 MMBtu 0 MMBtu |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 15.03 /MMBtu |
TOTAL ENERGY |
39,103 MMBtu 0 MMBtu |
$ 42,165 $ 0 |
6.94 % 0.00 % |
$ 9.36 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | N | $ 16,650 | $ 23,371 | 0.71 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 02 | view details |
CONTRACT A WOOD PALLET RECYCLING COMPANY | 3.5316 | N | $ 0 | $ 13,000 | 0.00 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 03 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | N | $ 240 | $ 3,000 | 0.08 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 04 | view details |
INSTALL SYSTEM TO COLLECT SCRAP | 4.4440 | N | $ 1,600 | $ 21,734 | 0.07 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 05 | view details |
RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | 2.3132 | N | $ 0 | $ 1,820 | 0.00 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||