Industrial Assessment Centers
Assessment #OR0570
| Assessment Year | 2011 |
|---|---|
| SIC | 2421 |
| SIC Description | Sawmills And Planing Mills, General |
| NAICS | 321113 |
| NAICS Description | Sawmills |
| Principal Product | Lumber |
| Sales | $ 19,292,000 |
| # of Employees | 125 |
| Plant Area (Sq.Ft.) | 3,484,000 |
| Annual Production | 47,730 Pieces |
| Production Hrs. Annual | 2,080 |
| Location (State) | OR |
| Yearly Energy Cost | $ 455,892 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
6,088,813 kWh | $ 294,506 | $ 0.048 /kWh |
- Demand Charge |
30,301 kW | $ 161,386 | $ 5.33 /kW |
- Electricity Fees |
- | $ 0 | - |
TOTAL ENERGY |
62,411 MMBtu | $ 455,892 | $ 7.30 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
2,026,300 kWh 0 kWh |
$ 100,249 $ 0 |
34.04 % 0.00 % |
$ 0.048 /kWh |
- Demand Charge |
0 kW 0 kW |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 5.33 /kW |
- Electricity Fees |
- |
$ 10,100 $ 0 |
0.00 % 0.00 % |
- |
TOTAL ENERGY |
20,586 MMBtu 0 MMBtu |
$ 104,612 $ 0 |
22.95 % 0.00 % |
$ 7.30 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
ELIMINATE OR REDUCE COMPRESSED AIR USED FOR COOLING, AGITATING LIQUIDS, MOVING PRODUCT, OR DRYING | 2.4232 | $ 1,120 | $ 19,863 | 0.06 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 02 | view details |
UPGRADE CONTROLS ON COMPRESSORS | 2.4224 | $ 2,250 | $ 6,640 | 0.34 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 03 | view details |
UPGRADE CONTROLS ON COMPRESSORS | 2.4224 | $ 12,010 | $ 21,600 | 0.56 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 04 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | $ 17,900 | $ 26,900 | 0.67 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 05 | view details |
UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | 2.6231 | $ 1,000 | $ 983 | 1.02 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 06 | view details |
REPLACE OVER-SIZE MOTORS AND PUMPS WITH OPTIMUM SIZE | 2.4131 | $ 750 | $ 695 | 1.08 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 07 | view details |
REPLACE OVER-SIZE MOTORS AND PUMPS WITH OPTIMUM SIZE | 2.4131 | $ 191,000 | $ 157,400 | 1.21 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 08 | view details |
MAKE A NEW BY-PRODUCT | 3.1182 | $ 156,000 | $ 91,432 | 1.71 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 09 | view details |
REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | 4.112 | $ 1,200,000 | $ 543,000 | 2.21 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 10 | view details |
INSTALL SKYLIGHTS | 2.7145 | $ 9,050 | $ 2,930 | 3.09 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 11 | view details |
OPTIMIZE PLANT POWER FACTOR | 2.3212 | $ 51,900 | $ 10,100 | 5.14 | |||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||