| Assessment Year | 2004 |
|---|---|
| SIC | 2435 |
| SIC Description | Hardwood Veneer And Plywood |
| NAICS | 321211 |
| NAICS Description | Hardwood Veneer and Plywood Manufacturing |
| Principal Product | Brad Beavers |
| Sales | $ 46,550,000 |
| # of Employees | 158 |
| Plant Area (Sq.Ft.) | 100,000 |
| Annual Production | 114,729 Tons |
| Production Hrs. Annual | 7,344 |
| Location (State) | OR |
| Yearly Energy Cost | $ 394,832 |
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
6,797,687 kWh | $ 164,020 | $ 0.024 /kWh |
- Demand Charge |
209,976 kW | $ 61,421 | $ 0.29 /kW |
- Electricity Fees |
- | $ 150,402 | - |
Natural Gas |
2,905 MMBtu | $ 18,989 | $ 6.54 /MMBtu |
TOTAL ENERGY |
72,581 MMBtu | $ 394,832 | $ 5.44 /MMBtu |
Water Disposal |
17,785,944 Gal | $ 22,716 | $ 0 /Gal |
Other Liquid (non-haz) |
62,084 Gal | $ 188 | $ 0 /Gal |
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
3,736,000 kWh 2,593,200 kWh |
$ 125,100 $ 86,900 |
76.27 % 52.98 % |
$ 0.024 /kWh |
- Demand Charge |
9,888 kW 5,728 kW |
$ 22,250 $ 16,900 |
36.23 % 27.52 % |
$ 0.29 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
0 MMBtu 0 MMBtu |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 6.54 /MMBtu |
TOTAL ENERGY |
38,866 MMBtu 26,581 MMBtu |
$ 154,850 $ 103,800 |
39.22 % 26.29 % |
$ 5.44 /MMBtu |
Water Disposal |
0 Gal 0 Gal |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 0 /Gal |
Other Liquid (non-haz) |
0 Gal 0 Gal |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 0 /Gal |
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | 2.5195 | N | $ 235 | $ 19,500 | 0.01 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 02 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 9,200 | $ 9,200 | 1.00 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 03 | view details |
REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH | 2.5121 | I | $ 0 | $ 3,000 | 0.00 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 04 | view details |
UPGRADE CONTROLS ON COMPRESSORS | 2.4224 | I | $ 1,200 | $ 22,000 | 0.05 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 05 | view details |
REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH | 2.5121 | N | $ 13,600 | $ 72,800 | 0.19 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 06 | view details |
INSTALL OCCUPANCY SENSORS | 2.7135 | N | $ 3,100 | $ 3,200 | 0.97 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 07 | view details |
USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | 2.4133 | I | $ 27,800 | $ 29,200 | 0.95 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 08 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 13,800 | $ 12,700 | 1.09 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 09 | view details |
REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH | 2.5121 | I | $ 15,700 | $ 14,800 | 1.06 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 10 | view details |
TURN OFF EQUIPMENT WHEN NOT IN USE | 2.6218 | I | $ 26,600 | $ 15,800 | 1.68 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 11 | view details |
USE ADJUSTABLE FREQUENCY DRIVE TO REPLACE THROTTLING SYSTEM | 2.4143 | N | $ 24,900 | $ 14,650 | 1.70 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 12 | view details |
INSTALL EQUIPMENT TO MOVE PRODUCT | 4.4450 | N | $ 242,000 | $ 102,400 | 2.36 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||