| Assessment Year | 2002 |
|---|---|
| SIC | 1041 |
| SIC Description | Gold Ores |
| NAICS | 0 |
| NAICS Description | |
| Principal Product | 2 |
| Sales | $ 287,732,044 |
| # of Employees | 1,462 |
| Plant Area (Sq.Ft.) | 0 |
| Annual Production | 0 Pounds |
| Production Hrs. Annual | 8,565 |
| Location (State) | NV |
| Yearly Energy Cost | $ 23,165,757 |
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
353,469,361 kWh | $ 17,414,720 | $ 0.049 /kWh |
- Demand Charge |
518,750 kW | $ 216,146 | $ 0.42 /kW |
- Electricity Fees |
- | $ 6,000 | - |
Natural Gas |
778,171 MMBtu | $ 2,151,480 | $ 2.76 /MMBtu |
LPG |
594,294 MMBtu | $ 3,377,411 | $ 5.68 /MMBtu |
TOTAL ENERGY |
4,995,526 MMBtu | $ 23,165,757 | $ 4.64 /MMBtu |
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
20,293,367 kWh 1,506,840 kWh |
$ 1,018,673 $ 73,000 |
5.85 % 0.42 % |
$ 0.049 /kWh |
- Demand Charge |
33,564 kW 1,964 kW |
$ 167,770 $ 9,820 |
77.62 % 4.54 % |
$ 0.42 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
205,705 MMBtu 5,582 MMBtu |
$ 770,766 $ 20,311 |
35.82 % 0.94 % |
$ 2.76 /MMBtu |
LPG |
0 MMBtu 0 MMBtu |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 5.68 /MMBtu |
TOTAL ENERGY |
413,713 MMBtu 21,028 MMBtu |
$ 1,957,209 $ 103,131 |
8.45 % 0.45 % |
$ 4.64 /MMBtu |
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
RELOCATE OVEN / FURNACE TO MORE EFFICIENT LOCATION | 2.1117 | P | $ 207,147 | $ 577,590 | 0.36 | ||||||||||||||||
|
|||||||||||||||||||||||
| 02 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | N | $ 1,727,000 | $ 958,574 | 1.80 | ||||||||||||||||
|
|||||||||||||||||||||||
| 03 | view details |
RECOVER HEAT FROM EXHAUSTED STEAM | 2.2445 | P | $ 118,500 | $ 158,150 | 0.75 | ||||||||||||||||
|
|||||||||||||||||||||||
| 04 | view details |
USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | 2.4133 | N | $ 241,870 | $ 119,700 | 2.02 | ||||||||||||||||
|
|||||||||||||||||||||||
| 05 | view details |
ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | 4.1110 | I | $ 46,000 | $ 69,350 | 0.66 | ||||||||||||||||
|
|||||||||||||||||||||||
| 06 | view details |
UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | 2.4111 | N | $ 0 | $ 25,349 | 0.00 | ||||||||||||||||
|
|||||||||||||||||||||||
| 07 | view details |
ADJUST BURNERS FOR EFFICIENT OPERATION | 2.1133 | I | $ 1,000 | $ 20,311 | 0.05 | ||||||||||||||||
|
|||||||||||||||||||||||
| 08 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 12,200 | $ 13,470 | 0.91 | ||||||||||||||||
|
|||||||||||||||||||||||
| 09 | view details |
ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | 4.1110 | N | $ 45,000 | $ 14,715 | 3.06 | ||||||||||||||||
|
|||||||||||||||||||||||