Assessment #NC0354
| Assessment Year | 2007 |
|---|---|
| SIC | 3724 |
| SIC Description | Aircraft Engines And Engine Parts |
| NAICS | 336412 |
| NAICS Description | Aircraft Engine and Engine Parts Manufacturing |
| Principal Product | Fuel controls |
| Sales | $ 250,000,000 |
| # of Employees | 335 |
| Plant Area (Sq.Ft.) | 220,000 |
| Annual Production | 7,500 Pieces |
| Production Hrs. Annual | 6,000 |
| Location (State) | NC |
| Yearly Energy Cost | $ 1,676,624 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
20,904,663 kWh | $ 1,189,598 | $ 0.057 /kWh |
- Demand Charge |
48,074 kW | $ 79,470 | $ 1.65 /kW |
- Electricity Fees |
- | $ 3,994 | - |
Natural Gas |
22,709 MMBtu | $ 403,562 | $ 17.77 /MMBtu |
TOTAL ENERGY |
236,982 MMBtu | $ 1,676,624 | $ 7.07 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
1,160,396 kWh 135,518 kWh |
$ 98,407 $ 7,711 |
8.27 % 0.65 % |
$ 0.057 /kWh |
- Demand Charge |
0 kW 0 kW |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 1.65 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
5,114 MMBtu 407 MMBtu |
$ 93,125 $ 7,411 |
23.08 % 1.84 % |
$ 17.77 /MMBtu |
TOTAL ENERGY |
17,008 MMBtu 1,796 MMBtu |
$ 191,532 $ 15,122 |
11.42 % 0.90 % |
$ 7.07 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | 2.2612 | N | $ 45,600 | $ 39,874 | 1.14 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 02 | view details |
RECOVER HEAT FROM AIR COMPRESSOR | 2.2434 | N | $ 100,000 | $ 32,774 | 3.05 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 03 | view details |
REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | 2.1321 | N | $ 100,000 | $ 65,972 | 1.52 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 04 | view details |
RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | 2.3131 | N | $ 2,000 | $ 35,076 | 0.06 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 05 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 100 | $ 2,375 | 0.04 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 06 | view details |
ADJUST BURNERS FOR EFFICIENT OPERATION | 2.1133 | I | $ 2,000 | $ 7,411 | 0.27 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 07 | view details |
REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | 2.1131 | N | $ 1,000 | $ 2,714 | 0.37 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 08 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 2,559 | $ 2,936 | 0.87 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||