Industrial Assessment Centers
Assessment #MS0378
| Assessment Year | 2011 |
|---|---|
| SIC | 3011 |
| SIC Description | Tires And Inner Tubes |
| NAICS | 326211 |
| NAICS Description | Tire Manufacturing (except Retreading) |
| Principal Product | Rubber Tires |
| Sales | $ 750,000,000 |
| # of Employees | 1,750 |
| Plant Area (Sq.Ft.) | 1,700,000 |
| Annual Production | 14,000,000 Pieces |
| Production Hrs. Annual | 8,760 |
| Location (State) | MS |
| Yearly Energy Cost | $ 10,398,275 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
126,518,370 kWh | $ 3,563,617 | $ 0.028 /kWh |
- Demand Charge |
203,013 kW | $ 2,057,874 | $ 10.14 /kW |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
589,976 MMBtu | $ 4,776,784 | $ 8.10 /MMBtu |
TOTAL ENERGY |
1,886,802 MMBtu | $ 10,398,275 | $ 5.51 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
887,296 kWh 0 kWh |
$ 24,845 $ 0 |
0.70 % 0.00 % |
$ 0.028 /kWh |
- Demand Charge |
1,215 kW 0 kW |
$ 12,328 $ 0 |
0.60 % 0.00 % |
$ 10.14 /kW |
- Electricity Fees |
- |
$ 557 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
0 MMBtu 0 MMBtu |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 8.10 /MMBtu |
TOTAL ENERGY |
9,095 MMBtu 0 MMBtu |
$ 37,730 $ 0 |
0.36 % 0.00 % |
$ 5.51 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | 2.2424 | N | $ 178,700 | $ 23,582 | 7.58 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 02 | view details |
USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | 2.2424 | N | $ 132,820 | $ 14,148 | 9.39 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||