Industrial Assessment Centers
Assessment #MS0318
| Assessment Year | 2007 |
|---|---|
| SIC | 2834 |
| SIC Description | Pharmaceutical Preparations |
| NAICS | 325412 |
| NAICS Description | Pharmaceutical Preparation Manufacturing |
| Principal Product | Pharmaceutical |
| Sales | $ 10,000,000 |
| # of Employees | 120 |
| Plant Area (Sq.Ft.) | 114,000 |
| Annual Production | 12,000,000 Not Available |
| Production Hrs. Annual | 2,080 |
| Location (State) | MS |
| Yearly Energy Cost | $ 128,050 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
1,314,760 kWh | $ 70,567 | $ 0.054 /kWh |
- Demand Charge |
4,435 kW | $ 31,425 | $ 7.09 /kW |
- Electricity Fees |
- | $ 1,438 | - |
Natural Gas |
1,233 MMBtu | $ 24,620 | $ 19.97 /MMBtu |
TOTAL ENERGY |
14,709 MMBtu | $ 128,050 | $ 8.71 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
187,964 kWh 186,868 kWh |
$ 7,678 $ 7,633 |
10.88 % 10.82 % |
$ 0.054 /kWh |
- Demand Charge |
674 kW 663 kW |
$ 9,618 $ 9,461 |
30.61 % 30.11 % |
$ 7.09 /kW |
- Electricity Fees |
- |
$ 259 $ 256 |
18.01 % 17.80 % |
- |
Natural Gas |
207 MMBtu 170 MMBtu |
$ 4,139 $ 3,392 |
16.81 % 13.78 % |
$ 19.97 /MMBtu |
TOTAL ENERGY |
2,133 MMBtu 2,085 MMBtu |
$ 21,694 $ 20,742 |
16.94 % 16.20 % |
$ 8.71 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 34,528 | $ 10,453 | 3.30 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 02 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 20,897 | $ 3,884 | 5.38 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 03 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 401 | $ 3,013 | 0.13 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 04 | view details |
REPAIR AND ELIMINATE STEAM LEAKS | 2.2135 | I | $ 156 | $ 2,805 | 0.06 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 05 | view details |
USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT COMBUSTION AIR | 2.2411 | N | $ 378 | $ 747 | 0.51 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 06 | view details |
ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | 2.1233 | I | $ 0 | $ 587 | 0.00 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 07 | view details |
UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | 2.4111 | N | $ 434 | $ 205 | 2.12 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||