Assessment #MAS013
| Assessment Year | 2011 |
|---|---|
| SIC | 2621 |
| SIC Description | Paper Mills |
| NAICS | 322121 |
| NAICS Description | Paper (except Newsprint) Mills |
| Principal Product | Paper Manufacturing and Converting |
| Sales | $ 42,000,000 |
| # of Employees | 100 |
| Plant Area (Sq.Ft.) | 200,000 |
| Annual Production | 28,000 Tons |
| Production Hrs. Annual | 6,000 |
| Location (State) | VT |
| Yearly Energy Cost | $ 5,578,033 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
23,114,900 kWh | $ 891,715 | $ 0.039 /kWh |
- Demand Charge |
112,907 kW | $ 1,305,318 | $ 11.56 /kW |
- Electricity Fees |
- | $ 0 | - |
Fuel Oil #6 |
143,782 MMBtu | $ 1,898,000 | $ 13.20 /MMBtu |
Other Energy |
96,288 MMBtu | $ 1,483,000 | $ 15.40 /MMBtu |
TOTAL ENERGY |
477,000 MMBtu | $ 5,578,033 | $ 11.69 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
-7,308 kWh 592,135 kWh |
$ -421 $ 34,166 |
-0.05 % 3.83 % |
$ 0.039 /kWh |
- Demand Charge |
-1,026 kW 317 kW |
$ -11,860 $ 3,664 |
-0.91 % 0.28 % |
$ 11.56 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Fuel Oil #6 |
4,615 MMBtu 0 MMBtu |
$ 65,072 $ 0 |
3.43 % 0.00 % |
$ 13.20 /MMBtu |
Other Energy |
425 MMBtu 425 MMBtu |
$ 5,993 $ 5,993 |
0.40 % 0.40 % |
$ 15.40 /MMBtu |
TOTAL ENERGY |
4,965 MMBtu 6,494 MMBtu |
$ 58,784 $ 43,823 |
1.05 % 0.79 % |
$ 11.69 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
UPGRADE OBSOLETE EQUIPMENT | 2.4321 | N | $ 42,112 | $ 27,730 | 1.52 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 02 | view details |
REPLACE OVER-SIZE MOTORS AND PUMPS WITH OPTIMUM SIZE | 2.4131 | I | $ 20,475 | $ 21,255 | 0.96 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 03 | view details |
UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | 2.4111 | I | $ 0 | $ 12,053 | 0.00 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 04 | view details |
REPLACE OVER-SIZE MOTORS AND PUMPS WITH OPTIMUM SIZE | 2.4131 | N | $ 15,000 | $ 7,289 | 2.06 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 05 | view details |
INSULATE BARE EQUIPMENT | 2.2511 | I | $ 3,600 | $ 3,878 | 0.93 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 06 | view details |
REPLACE OVER-SIZE MOTORS AND PUMPS WITH OPTIMUM SIZE | 2.4131 | I | $ 8,000 | $ 3,738 | 2.14 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 07 | view details |
TURN OFF STEAM / HOT WATER LINES LEADING TO SPACE HEATING UNITS | 2.6213 | I | $ 150 | $ 2,115 | 0.07 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 08 | view details |
REPLACE OVER-SIZE MOTORS AND PUMPS WITH OPTIMUM SIZE | 2.4131 | N | $ 5,000 | $ 942 | 5.31 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
| 09 | view details |
USE MORE EFFICIENT LIGHT SOURCE | 2.7143 | I | $ 3,500 | $ 784 | 4.46 | ||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||