Industrial Assessment Centers
Assessment #MA0589
| Assessment Year | 2006 |
|---|---|
| SIC | 3841 |
| SIC Description | Surgical And Medical Instruments |
| NAICS | 339112 |
| NAICS Description | Surgical and Medical Instrument Manufacturing |
| Principal Product | Silicone mouldings and hoses |
| Sales | $ 13,500,000 |
| # of Employees | 66 |
| Plant Area (Sq.Ft.) | 22,000 |
| Annual Production | 363 Tons |
| Production Hrs. Annual | 6,240 |
| Location (State) | MA |
| Yearly Energy Cost | $ 193,275 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
1,783,200 kWh | $ 102,578 | $ 0.058 /kWh |
- Demand Charge |
6,078 kW | $ 67,192 | $ 11.05 /kW |
- Electricity Fees |
- | $ 6,106 | - |
Natural Gas |
1,297 MMBtu | $ 17,399 | $ 13.41 /MMBtu |
TOTAL ENERGY |
19,575 MMBtu | $ 193,275 | $ 9.87 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
920,382 kWh 129,348 kWh |
$ 53,875 $ 8,018 |
52.52 % 7.82 % |
$ 0.058 /kWh |
- Demand Charge |
2,199 kW 97 kW |
$ 27,203 $ 1,202 |
40.49 % 1.79 % |
$ 11.05 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
-1,976 MMBtu 59 MMBtu |
$ -25,669 $ 766 |
-147.53 % 4.40 % |
$ 13.41 /MMBtu |
TOTAL ENERGY |
7,457 MMBtu 1,384 MMBtu |
$ 55,409 $ 9,986 |
28.67 % 5.17 % |
$ 9.87 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
BURN A LESS EXPENSIVE GRADE OF FUEL | 2.1331 | N | $ 95,420 | $ 29,215 | 3.27 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 02 | view details |
USE MINIMUM SAFE OVEN VENTILATION | 2.2212 | N | $ 1,600 | $ 13,600 | 0.12 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 03 | view details |
USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | 2.2614 | I | $ 4,000 | $ 3,300 | 1.21 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 04 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | N | $ 10,890 | $ 2,608 | 4.18 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 05 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | I | $ 3,565 | $ 2,311 | 1.54 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 06 | view details |
RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | 2.2531 | I | $ 400 | $ 1,951 | 0.21 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 07 | view details |
INSULATE BARE EQUIPMENT | 2.2511 | I | $ 1,800 | $ 2,060 | 0.87 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 08 | view details |
INSULATE BARE EQUIPMENT | 2.2511 | I | $ 60 | $ 187 | 0.32 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 09 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 800 | $ 177 | 4.52 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||