Industrial Assessment Centers
Assessment #KU0548
| Assessment Year | 2000 |
|---|---|
| SIC | 3825 |
| SIC Description | Instruments To Measure Electricity |
| NAICS | |
| NAICS Description | |
| Principal Product | electrical metering equipment |
| Sales | $ 33,000,000 |
| # of Employees | 200 |
| Plant Area (Sq.Ft.) | 108,800 |
| Annual Production | 432,000 Not Available |
| Production Hrs. Annual | 4,500 |
| Location (State) | MO |
| Yearly Energy Cost | $ 263,602 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
2,810,906 kWh | $ 123,116 | $ 0.044 /kWh |
- Demand Charge |
8,299 kW | $ 35,839 | $ 4.32 /kW |
- Electricity Fees |
- | $ 23,433 | - |
Natural Gas |
14,516 MMBtu | $ 81,214 | $ 5.59 /MMBtu |
TOTAL ENERGY |
43,328 MMBtu | $ 263,602 | $ 6.08 /MMBtu |
Water Disposal |
5,984,154 Gal | $ 10,400 | $ 0 /Gal |
Other Liquid (haz) |
100 Gal | $ 0 | $ 0 /Gal |
Solid Waste (non-haz) |
1,140,710 lbs | $ -115,805 | $ 0 /lbs |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
178,195 kWh 0 kWh |
$ 6,991 $ 0 |
5.68 % 0.00 % |
$ 0.044 /kWh |
- Demand Charge |
483 kW 0 kW |
$ 4,189 $ 0 |
11.69 % 0.00 % |
$ 4.32 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
1,218 MMBtu 0 MMBtu |
$ 6,808 $ 0 |
8.38 % 0.00 % |
$ 5.59 /MMBtu |
TOTAL ENERGY |
3,045 MMBtu 0 MMBtu |
$ 17,988 $ 0 |
6.82 % 0.00 % |
$ 6.08 /MMBtu |
Water Disposal |
130,650 Gal 0 Gal |
$ 1,698 $ 0 |
16.33 % 0.00 % |
$ 0 /Gal |
Other Liquid (haz) |
0 Gal 0 Gal |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 0 /Gal |
Solid Waste (non-haz) |
0 lbs 0 lbs |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 0 /lbs |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | 2.8113 | K | $ 0 | $ 13,917 | 0.00 | ||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||
| 02 | view details |
USE / PURCHASE OPTIMUM SIZED COMPRESSOR | 2.4226 | K | $ 11,500 | $ 6,154 | 1.87 | ||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||
| 03 | view details |
RECOVER HEAT FROM AIR COMPRESSOR | 2.2434 | K | $ 1,505 | $ 3,963 | 0.38 | ||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||
| 04 | view details |
REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | 2.4231 | K | $ 40 | $ 2,604 | 0.02 | ||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||
| 05 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | K | $ 1,050 | $ 2,422 | 0.43 | ||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||
| 06 | view details |
MINIMIZE WATER USAGE | 3.4151 | K | $ 4,075 | $ 4,075 | 1.00 | ||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||