Assessment #KU0163
| Assessment Year | 1985 |
|---|---|
| SIC | 3366 |
| SIC Description | Copper Foundries |
| NAICS | |
| NAICS Description | |
| Principal Product | METAL CASTINGS |
| Sales | $ 4,500,000 |
| # of Employees | 70 |
| Plant Area (Sq.Ft.) | 0 |
| Annual Production | 800,000 Pounds |
| Production Hrs. Annual | 2,100 |
| Location (State) | KS |
| Yearly Energy Cost | $ 174,471 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
2,625,147 kWh | $ 145,257 | $ 0.055 /kWh |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
6,207 MMBtu | $ 29,214 | $ 4.71 /MMBtu |
TOTAL ENERGY |
33,115 MMBtu | $ 174,471 | $ 5.27 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
188,161 kWh 84,702 kWh |
$ 10,414 $ 4,688 |
7.17 % 3.23 % |
$ 0.055 /kWh |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
1,889 MMBtu 1,008 MMBtu |
$ 9,646 $ 4,749 |
33.02 % 16.26 % |
$ 4.71 /MMBtu |
TOTAL ENERGY |
3,817 MMBtu 1,876 MMBtu |
$ 20,060 $ 9,437 |
11.50 % 5.41 % |
$ 5.27 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | 2.2444 | N | $ 10,700 | $ 12,428 | 0.86 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 02 | view details |
USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | 2.4322 | I | $ 500 | $ 2,439 | 0.21 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 03 | view details |
RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT | 2.1122 | I | $ 400 | $ 461 | 0.87 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 04 | view details |
INSULATE BARE EQUIPMENT | 2.2511 | I | $ 60 | $ 499 | 0.12 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 05 | view details |
TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | 2.6212 | N | $ 50 | $ 1,087 | 0.05 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 06 | view details |
TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | 2.6212 | I | $ 0 | $ 979 | 0.00 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 07 | view details |
RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | 2.2443 | N | $ 4,200 | $ 2,124 | 1.98 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 08 | view details |
RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | 2.2443 | N | $ 750 | $ 400 | 1.88 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 09 | view details |
MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | 2.7312 | I | $ 140 | $ 462 | 0.30 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 10 | view details |
REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | 2.4231 | N | $ 50 | $ 1,233 | 0.04 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 11 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 180 | $ 130 | 1.38 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 12 | view details |
TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | 2.6212 | I | $ 455 | $ 357 | 1.27 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 13 | view details |
TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | 2.6212 | I | $ 175 | $ 324 | 0.54 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 14 | view details |
RECOVER WASTE HEAT FROM EQUIPMENT | 2.2437 | N | $ 500 | $ 1,054 | 0.47 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 15 | view details |
IMPROVE LUBRICATION PRACTICES | 2.4312 | N | $ 1,016 | $ 1,119 | 0.91 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 16 | view details |
INSTALL TIMERS AND/OR THERMOSTATS | 2.7261 | I | $ 1,000 | $ 2,273 | 0.44 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 17 | view details |
INSTALL AUTOMATIC STACK DAMPER | 2.1123 | I | $ 900 | $ 363 | 2.48 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 18 | view details |
SHUT OFF PILOTS IN STANDBY EQUIPMENT | 2.6214 | I | $ 0 | $ 160 | 0.00 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 19 | view details |
ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | 2.1233 | N | $ 0 | $ 11 | 0.00 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 20 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | N | $ 2,874 | $ 2,287 | 1.26 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||