Industrial Assessment Centers
Assessment #IA0441
| Assessment Year | 2009 |
|---|---|
| SIC | 3069 |
| SIC Description | Fabricated Rubber Products, Nec |
| NAICS | 326220 |
| NAICS Description | Rubber and Plastics Hoses and Belting Manufacturing |
| Principal Product | Industrail hose |
| Sales | $ 90,000,000 |
| # of Employees | 350 |
| Plant Area (Sq.Ft.) | 280,000 |
| Annual Production | 22,000,000 Pounds |
| Production Hrs. Annual | 6,240 |
| Location (State) | Ne |
| Yearly Energy Cost | $ 1,442,634 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
20,085,793 kWh | $ 660,798 | $ 0.033 /kWh |
- Demand Charge |
34,464 kW | $ 248,414 | $ 7.21 /kW |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
64,514 MMBtu | $ 533,422 | $ 8.27 /MMBtu |
TOTAL ENERGY |
270,393 MMBtu | $ 1,442,634 | $ 5.34 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
1,967,315 kWh 1,351,837 kWh |
$ 64,138 $ 43,959 |
9.71 % 6.65 % |
$ 0.033 /kWh |
- Demand Charge |
689 kW 102 kW |
$ 4,816 $ 724 |
1.94 % 0.29 % |
$ 7.21 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
6,322 MMBtu 259 MMBtu |
$ 51,906 $ 2,129 |
9.73 % 0.40 % |
$ 8.27 /MMBtu |
TOTAL ENERGY |
26,487 MMBtu 14,115 MMBtu |
$ 120,860 $ 46,812 |
8.38 % 3.24 % |
$ 5.34 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | 2.4133 | N | $ 680 | $ 2,701 | 0.25 | ||||||||||||||||
|
|||||||||||||||||||||||
| 02 | view details |
UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | 2.4111 | N | $ 17,051 | $ 7,759 | 2.20 | ||||||||||||||||
|
|||||||||||||||||||||||
| 03 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 702 | $ 2,444 | 0.29 | ||||||||||||||||
|
|||||||||||||||||||||||
| 04 | view details |
INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | 2.4221 | N | $ 825 | $ 1,935 | 0.43 | ||||||||||||||||
|
|||||||||||||||||||||||
| 05 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | N | $ 650 | $ 4,456 | 0.15 | ||||||||||||||||
|
|||||||||||||||||||||||
| 06 | view details |
ELIMINATE OR REDUCE COMPRESSED AIR USED FOR COOLING, AGITATING LIQUIDS, MOVING PRODUCT, OR DRYING | 2.4232 | N | $ 1,820 | $ 7,420 | 0.25 | ||||||||||||||||
|
|||||||||||||||||||||||
| 07 | view details |
INSTALL OCCUPANCY SENSORS | 2.7135 | I | $ 479 | $ 853 | 0.56 | ||||||||||||||||
|
|||||||||||||||||||||||
| 08 | view details |
INSULATE STEAM / HOT WATER LINES | 2.2131 | I | $ 760 | $ 2,129 | 0.36 | ||||||||||||||||
|
|||||||||||||||||||||||
| 09 | view details |
REDUCE COMBUSTION AIR FLOW TO OPTIMUM | 2.1113 | N | $ 70,000 | $ 49,777 | 1.41 | ||||||||||||||||
|
|||||||||||||||||||||||
| 10 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | I | $ 27,000 | $ 25,097 | 1.08 | ||||||||||||||||
|
|||||||||||||||||||||||
| 11 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | I | $ 16,600 | $ 16,289 | 1.02 | ||||||||||||||||
|
|||||||||||||||||||||||