Industrial Assessment Centers
Assessment #DL0053
| Assessment Year | 2010 |
|---|---|
| SIC | 2834 |
| SIC Description | Pharmaceutical Preparations |
| NAICS | 325412 |
| NAICS Description | Pharmaceutical Preparation Manufacturing |
| Principal Product | Pharmaceuticals |
| Sales | $ 56,000,000 |
| # of Employees | 400 |
| Plant Area (Sq.Ft.) | 612,277 |
| Annual Production | 1 Not Available |
| Production Hrs. Annual | 4,210 |
| Location (State) | DE |
| Yearly Energy Cost | $ 5,506,609 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
35,762,484 kWh | $ 3,618,409 | $ 0.101 /kWh |
- Demand Charge |
5,341 kW | $ 16,235 | $ 3.04 /kW |
- Electricity Fees |
- | $ 0 | - |
Natural Gas |
187,861 MMBtu | $ 1,871,965 | $ 9.96 /MMBtu |
TOTAL ENERGY |
554,426 MMBtu | $ 5,506,609 | $ 9.93 /MMBtu |
Water Disposal |
21,093,000 Gal | $ 93,052 | $ 0 /Gal |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
4,722,522 kWh 4,586,522 kWh |
$ 497,000 $ 482,900 |
13.74 % 13.35 % |
$ 0.101 /kWh |
- Demand Charge |
0 kW 0 kW |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 3.04 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
56,206 MMBtu 36,386 MMBtu |
$ 541,600 $ 344,600 |
28.93 % 18.41 % |
$ 9.96 /MMBtu |
TOTAL ENERGY |
104,613 MMBtu 83,399 MMBtu |
$ 1,038,600 $ 827,500 |
18.86 % 15.03 % |
$ 9.93 /MMBtu |
Water Disposal |
0 Gal 0 Gal |
$ 0 $ 0 |
0.00 % 0.00 % |
$ 0 /Gal |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | 2.7221 | I | $ 4,000 | $ 358,000 | 0.01 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 02 | view details |
USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | 2.6221 | N | $ 760 | $ 142,000 | 0.01 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 03 | view details |
ADD AREA LIGHTING SWITCHES | 2.7131 | I | $ 29,200 | $ 123,000 | 0.24 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 04 | view details |
INCREASE AMOUNT OF CONDENSATE RETURNED | 2.2121 | I | $ 60,000 | $ 58,000 | 1.03 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 05 | view details |
ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | 2.1233 | I | $ 30,000 | $ 80,000 | 0.38 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 06 | view details |
ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | 2.4236 | I | $ 700 | $ 74,000 | 0.01 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 07 | view details |
RECOVER HEAT FROM AIR COMPRESSOR | 2.2434 | N | $ 10,000 | $ 55,000 | 0.18 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 08 | view details |
USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | 2.6221 | I | $ 20 | $ 61,000 | 0.00 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 09 | view details |
UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | 2.4111 | I | $ 10,240 | $ 40,900 | 0.25 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 10 | view details |
INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | 2.4221 | N | $ 1,920 | $ 10,000 | 0.19 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 11 | view details |
TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | 2.6212 | I | $ 10 | $ 6,000 | 0.00 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 12 | view details |
REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | 2.4231 | N | $ 500 | $ 4,100 | 0.12 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 13 | view details |
LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | 2.7221 | I | $ 100 | $ 2,600 | 0.04 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 14 | view details |
ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | 2.6124 | I | $ 8,600 | $ 18,000 | 0.48 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||
| 15 | view details |
USE MULTIPLE SPEED MOTORS OR AFD FOR VARIABLE PUMP, BLOWER AND COMPRESSOR LOADS | 2.4141 | I | $ 31,440 | $ 25,000 | 1.26 | ||||||||||||||||||||
|
|||||||||||||||||||||||||||