Assessment #CO0519
| Assessment Year | 2002 |
|---|---|
| SIC | 2099 |
| SIC Description | Food Preparations, Nec |
| NAICS | 311411 |
| NAICS Description | Frozen Fruit, Juice, and Vegetable Manufacturing |
| Principal Product | frozen green chile peppers, tortillas |
| Sales | $ 50,000,000 |
| # of Employees | 200 |
| Plant Area (Sq.Ft.) | 120,500 |
| Annual Production | 8,000,000 Pounds |
| Production Hrs. Annual | 6,552 |
| Location (State) | NM |
| Yearly Energy Cost | $ 505,296 |
Current Energy Usage & Costs
| Energy Sources | Yearly Usage | Yearly Cost | Unit Price |
|---|---|---|---|
Electricity |
6,307,200 kWh | $ 253,401 | $ 0.040 /kWh |
- Demand Charge |
11,979 kW | $ 69,241 | $ 5.78 /kW |
- Electricity Fees |
- | $ 70,732 | - |
Natural Gas |
26,748 MMBtu | $ 111,922 | $ 4.18 /MMBtu |
TOTAL ENERGY |
91,397 MMBtu | $ 505,296 | $ 5.53 /MMBtu |
Recommended Reduction in Usage & Costs
|
Recommended Implemented |
| Energy Sources | Yearly Savings | Yearly Cost | % Saved | Unit Price |
|---|---|---|---|---|
Electricity |
117,351 kWh 72,251 kWh |
$ 4,758 $ 2,908 |
1.88 % 1.15 % |
$ 0.040 /kWh |
- Demand Charge |
188 kW 112 kW |
$ 2,165 $ 1,285 |
3.13 % 1.86 % |
$ 5.78 /kW |
- Electricity Fees |
- |
$ 0 $ 0 |
0.00 % 0.00 % |
- |
Natural Gas |
1,171 MMBtu 0 MMBtu |
$ 4,990 $ 0 |
4.46 % 0.00 % |
$ 4.18 /MMBtu |
TOTAL ENERGY |
2,374 MMBtu 741 MMBtu |
$ 11,913 $ 4,193 |
2.36 % 0.83 % |
$ 5.53 /MMBtu |
Recommendations
| AR # | Description | ARC Code | Status | Cost | Savings | Payback (Years) |
|||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | view details |
INSULATE BARE EQUIPMENT | 2.2511 | N | $ 1,350 | $ 5,560 | 0.24 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 02 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 5,292 | $ 2,972 | 1.78 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 03 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 3,156 | $ 954 | 3.31 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 04 | view details |
UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | 2.4111 | N | $ 2,700 | $ 1,390 | 1.94 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 05 | view details |
INSTALL COMMON HEADER ON COMPRESSORS | 2.4225 | N | $ 2,740 | $ 770 | 3.56 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 06 | view details |
USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | 2.4133 | I | $ 280 | $ 103 | 2.72 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
| 07 | view details |
UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | 2.7142 | I | $ 742 | $ 286 | 2.59 | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||